Murray Basin Hydrogeological Project : progress report 5 for half year ending 31 March 1981
Published by Geoscience Australia Data
About this dataset
The groundwater modelling sub-committee set up by the Steering Committee in June 1980, met in October and recommended that a preliminary model of the Basin should be attempted; it should contain 3 layers, with a 10 x 10 grid (300 nodes) and have the aim of increasing theaccuracy of solutions at later stages by decreasing the grid size. The sub-committee proposed that a whole basin model be attempted by the South Australian Department of Mines & Energy using a finite element method, and by the Water Resources Commission of New South Wales using a finite difference approach; the methods could then be compared before a more elaborate model was tried.